North Parkway Construction, News, and Impacts

GWMP Construction Infographic
This infographic displays the areas that are under construction and the anticipated schedule.

NPS

Construction efforts to rehabilitate the George Washing Memorial Parkway (GWMP) are underway between I-495 and Spout Run Parkway. Construction activities will impact drivers and park visitors for the duration of the rehabilitation. View construction updates under Current Construction. The project is anticipated to be completed in late 2025.

  • To opt in to receive email updates about traffic, meeting notices and information about major milestones please click here.
  • To contact the project team please e-mail us. 
  • View recordings of informational public meetings on our public meeting webpage.

Rehabilitation Progress Along the Parkway

Crews continue to make progress on rehabilitation work daily. As of Spring 2024:

  • 26% of the roadway has been replaced, improving drivability and safety. 
  • 45% of the guardwall has been repaired or replaced, upgrading motorist safety.
  • 60% of the drainage work is complete, reducing erosion and sediment run off.
  • 40% of the outfalls have been repaired, improving drainage structures that discharge water to nearby streams.
  • 45% of the bridge repairs are complete, rehabilitating aging infrastructure. 
 
A graphic depicting how the new traffic arrangement will look.
During the morning rush hour, two lanes will carry traffic southbound toward Washington, DC. During the evening rush hour, two lanes will carry traffic northbound toward Maryland.

NPS

Current Construction (Updated June 2024)

I-495 to Route 123


The National Park Service (NPS) has entered the next phase of the North Parkway Rehabilitation Project. In January, the three-lane traffic pattern, with a reversible lane, between I-495 and Route 123 shifted from the northbound lanes to the southbound lanes of the parkway. The NPS expects this three-lane traffic pattern to be in effect through late 2025. Crews continue repairs on the northbound side of the parkway, including reconstructing the existing roadway, curb, drainage, and masonry guard wall.

Lane Configuration:

  • Temporary Lane: The temporary lane remains in place in the median of the parkway between the Route 123 interchange and I-495. This temporary lane will always travel north and drivers heading toward Maryland must use this lane.
  • Southbound Lane / Center Lane: The southbound lane closest to the median (or center lane) is a reversible lane and will change direction to travel southbound during the morning rush hour and northbound during the evening rush hour. This lane is closed outside of weekday rush hour, on weekends and holidays.
  • Southbound Lane: The southbound lane next to the outside shoulder lane will always travel south.
Reversible Lane Schedule
The three-lane configuration extends from I-495 to the Route 123 Interchange. The reversible lane schedule is as follows:

Weekday morning rush hour (5:30 a.m. – 9:30 a.m.)
  • Two lanes southbound (toward Washington, DC).
  • One lane northbound (toward Maryland/Virginia).
Weekday evening rush hour (2:45 p.m. – 7:15 p.m.)
  • Two lanes northbound (toward Maryland/Virginia).
  • One lane southbound (toward Washington, DC).
Weekdays (9:30 a.m. – 2:45 p.m. and 7:15 p.m. - 5:30 a.m.) weekends and major holidays
  • One lane southbound (toward Washington, DC).
  • One lane northbound (toward Maryland/Virginia).
To increase safety, small physical barriers divide the narrow travel lanes. Commercial vehicles are restricted from the parkway at all times. Signage will direct drivers to the appropriate lanes. During non-rush hour periods, weekends, and holidays, the center reversible lane will be closed, and motorists can expect two travel lanes: one travelling northbound and one travelling southbound. The NPS expects the three-lane traffic pattern to be in effect through late 2025.
 
A map of the detour route
Detour route for Southbound Route 123 to Southeast GWMP.

NPS

Route 123 Interchange Ramp Weekend Detours


Crews continue rehabilitation activities and weekend ramp closures at the Route 123 interchange through Spring. Construction activities requiring the ramp closures include select tree removal, drainage installation, installation of permanent asphalt pavement, and and temporary widening activities. Detours will be in place as shown within the closure details.

Crews continue drainage work on the ramp from southbound Route 123 to southeast GWMP. The ramp closures will resume during weekends to complete activities as shown below:

  • Weekdays between 8 a.m. – 4 p.m. for curb construction.

  • Continuous weekend closure starting each Friday at 8 p.m. continuing through to Sunday at 11:59 p.m. for drainage installation and permanent asphalt paving.

 

Once this work is complete, construction crews will begin work on the ramp from northbound Route 123 to southeast GWMP, followed by the ramp from southeast GWMP to southbound Route 123.

 
Route 123 to Spout Run Parkway Construction Outlook
As part of the next phase of the North Parkway Rehabilitation Project, the outside (right) northbound lane of GWMP will be closed from June 29 through late August 2024 between the Route 123 interchange and Spout Run Parkway. There will be no reversible lane in this section of the Parkway.

Lane Configuration: June – August 2024
  • AM Rush Hour (5:30-9:30 a.m.): One lane will carry traffic northbound toward Maryland/Virginia and two lanes will carry traffic southbound toward D.C.
  • All other times: There will be one lane open to traffic in each direction.
On select weekends, both northbound lanes will be closed to allow crews to perform drainage and utility work. During this time, northbound traffic will be detoured from Spout Run Parkway to Glebe Road to Route 123. The NPS will provide more details ahead of each detour. Learn more about construction activities in each segment below.
 
A graphic depicting work occurring in the left most lane while three other lanes have traffic.
During the morning rush hour, one lane will carry traffic northbound toward Maryland/Virginia and two lanes will carry traffic southbound toward D.C. There will be one lane of traffic in each direction at all other times.

NPS

Route 123 to Windy Run Bridge

The right northbound lane is closed through late August for rehabilitation work including:

  • Drainage installation
  • Guardwall and curb reconstruction
  • Water erosion control activities
  • Pipe installation for electrical wiring

Roadway demolition for upcoming paving and temporary widening activities are underway at the Route 123 interchange ahead of the next traffic shift anticipated in late August. These activities are expected to continue through the Spring.

Through the Fall of 2024, both the North Donaldson Overlook and Fort Marcy will be inaccessible from the northbound right lane during non-rush hour times (9 a.m. - 2 p.m.). This configuration extends the existing right lane closure to allow for additional safe work zones for the expedition of rehabilitation work along the northbound shoulder.

 
A graphic depicting the set up of the traffic lanes.
Phase 1 of the northbound lane traffic shift will close the outer (right) travel lane. Only one lane will carry traffic northbound toward Maryland and Virginia at all times. During the morning rush hour only, two lanes will carry traffic southbound toward D.C; there will be one lane southbound.

NPS

Windy Run Bridge to Spout Run Parkway

The right northbound lane will be closed through late August for rehabilitation activities including:

  • Excavation and drainage structure installation
  • Guardwall repairs
  • Curb demolition
  • Water and erosion control activities
 
Future Phases
There will be additional traffic changes later this fall as the project progresses.
  • Spout Run Parkway to Windy Run Bridge: The NPS expects to shift traffic from the inner (left) to the outer (right) northbound lane in mid-fall through late 2024. The northbound lanes will both reopen upon completion in late 2024. Long-term lane closures on the southbound lanes are scheduled for spring 2025 through late 2025.
  • Windy Run Bridge to Route 123: The NPS plans to shift traffic to the northbound lanes this fall. Long-term lane closures will continue beyond late 2024.
The NPS will share more details before each traffic shift. All work is weather permitting and subject to change.
 
A graphic depicts construction workers in the Southbound lane, while traffic moves in three lanes (two nouthbound and one sorthbound) next to it.
During bridge work, a three-lane configuration will be in place with a barrier to separate traffic from the work zone.

NPS

Bridge Construction

Crews continue with bridge work:

  • Turkey Run, Donaldson Run, Glebe Road, Windy Run, Dead Run, and Gulf Branch Bridges: Repairs on and below the bridge surface.
  • Donaldson Run Bridge: Containment platform installation and perform repairs below the bridge surface.
  • The containment platform remains in place at Turkey Run loop with limited clearance between the platform and the bridge.

Temporary barriers remain in place at Pimmit Run, Glebe Road, Gulf Branch, Donaldson Run, Dead Run, Windy Run, and Turkey Run bridges with narrower lane widths as work continues. No additional traffic delays are anticipated at this time.

 

Construction Zone Safety

Please slow down and be cautious while driving through work zones on the parkway.

  • Drivers should observe traffic signs for updated information.
  • A 40 MPH speed limit remains in effect from the I-495 interchange to Spout Run Parkway to help keep construction crew and motorists safe. This speed limit will be in place for the remainder of the project and is enforced as such.
  • To avoid traffic delays on the northern section of the parkway, drivers should consider alternate routes and plan for additional travel time.
  • Remember vehicles over 10,000 lbs. are always prohibited from using the parkway.
 

Potomac Heritage National Trail Partially Closed through Late Fall 2024

A portion of the Potomac Heritage National Trail is closed under the Glebe Road Bridge for safety reasons. Crews installed containment platforms for blasting and painting activities under the bridge limiting space between the bridge and pedestrian trail. The partial closure of the trail is in place through the late Fall of 2024 as a safe detour is unavailable. Signage has been posted at trail entrance and exit points. Click here for more information on the trail closure.

 

Construction Signage on the North Parkway

 
Map of the North Parkway with Construction Signage
This is the temporary construction signage motorists will see while traveling along the North Parkway.

NPS

 
 

Frequently Asked Questions (FAQs)

 
Aerial view of Route 123 and the proposed GWMP Interchange Option One. The curved sections in purple would be removed and the proposed configuration is in blue and is more linear. The Limits of Disturbance boundary is a dashed yellow line.
 

North Parkway News

Loading results...

    Park footer

    Contact Info

    Mailing Address:

    George Washington Memorial Parkway Headquarters
    700 George Washington Memorial Parkway

    McLean, VA 22101

    Phone:

    703 289-2500

    Contact Us