North Parkway Construction, News, and Impacts

GWMP Construction Infographic
This infographic displays the areas that are under construction and the anticipated schedule.

NPS

Construction efforts to rehabilitate the George Washington Memorial Parkway (GWMP) are underway between I-495 and Spout Run Parkway. Construction activities will impact drivers and park visitors for the duration of the rehabilitation. View construction updates under Current Construction. The project is anticipated to be completed in late 2025.

  • To opt in to receive email updates about traffic, meeting notices and information about major milestones please click here.
  • To contact the project team please e-mail us. 
  • View recordings of informational public meetings on our public meeting webpage.

Rehabilitation Progress Along the Parkway

Crews continue to make progress on rehabilitation work daily. As of Spring 2025:

  • 55% of the roadway has been replaced, improving drivability and safety. 
  • 75% of the guardwall has been repaired or replaced, upgrading motorist safety.
  • 80% of the drainage work is complete, reducing erosion and sediment run off.
  • 65% of the bridge repairs are complete, rehabilitating aging infrastructure.
  • 100% of the outfalls have been repaired, completing works to improve drainage structures that discharge water to nearby streams.
 
A graphic depicting how the new traffic arrangement will look.
During the morning rush hour, two lanes will carry traffic southbound toward Washington, DC. During the evening rush hour, two lanes will carry traffic northbound toward Maryland.

NPS

Current Construction (Updated April 2025)

I-495 to Route 123


The National Park Service (NPS) continues working on the northbound lanes in this segment. In January 2024, the three-lane traffic pattern, with a reversible lane, between I-495 and Route 123 shifted from the northbound lanes to the southbound lanes of the parkway. The NPS expects this three-lane traffic pattern to be in effect through late 2025. Crews continue temporary lane demolition and reconstructing the curb, drainage, and masonry guard wall through mid 2025. Crews began landscaping and planting trees at ramps along the parkway. Drainage installation, roadway demolition, paving activities continue resulting in temporary traffic closures detailed below.

Lane Configuration:

  • Temporary Lane: The temporary lane remains in place in the median of the parkway between the Route 123 interchange and I-495. This temporary lane will always travel north and drivers heading toward Maryland must use this lane.
  • Southbound Lane / Center Lane: The southbound lane closest to the median (or center lane) is a reversible lane and will change direction to travel southbound during the morning rush hour and northbound during the evening rush hour. This lane is closed outside of weekday rush hour, on weekends and holidays.
  • Southbound Lane: The southbound lane next to the outside shoulder lane will always travel south.
Reversible Lane Schedule
The three-lane configuration extends from I-495 to the Route 123 Interchange. The reversible lane schedule is as follows:

Weekday morning rush hour (5:30 a.m. – 9:30 a.m.)
  • Two lanes southbound (toward Washington, DC).
  • One lane northbound (toward Maryland/Virginia).
Weekday evening rush hour (2:45 p.m. – 7:15 p.m.)
  • Two lanes northbound (toward Maryland/Virginia).
  • One lane southbound (toward Washington, DC).
Weekdays (9:30 a.m. – 2:45 p.m. and 7:15 p.m. - 5:30 a.m.) weekends and major holidays
  • One lane southbound (toward Washington, DC).
  • One lane northbound (toward Maryland/Virginia).
To increase safety, small physical barriers divide the narrow travel lanes. Commercial vehicles are restricted from the parkway at all times. Signage will direct drivers to the appropriate lanes. During non-rush hour periods, weekends, and holidays, the center reversible lane will be closed, and motorists can expect two travel lanes: one travelling northbound and one travelling southbound. The NPS expects the three-lane traffic pattern to be in effect through late 2025.
 
Map of GWMP Turkey Run Ramp Closure
Motorists traveling on NB GWMP should continue to I-495 south, turn at Georgetown Pike and proceed to SB GWMP.

NPS

Turkey Run Loop Exit to/from Northbound GWMP Closed through Late April for Rehabilitation Work

The exit to and from Turkey Run Park from northbound GWMP is closed through late April, weather permitting, for roadway demolition and asphalt paving on the northbound lanes. During this time, Turkey Run loop will only be accessible from southbound GWMP. Additionally, motorists traveling southbound on GWMP will not be able to use the Turkey Run loop to cross the parkway and access northbound GWMP. Motorists traveling on Turkey Run Loop Road will only have access to southbound GWMP.

Detour Information: To reach Turkey Run Loop Road: Northbound GWMP drivers should continue to I-495 south, turn at Georgetown Pike, and proceed to southbound GWMP to Turkey Run Loop Road.
 
Map of GWMP Turkey Run SB to NB Detour
Motorists leaving Turkey Run Park will only have access to southbound GWMP. To access northbound GWMP, motorists should continue southbound on GWMP to Route 123 to access northbound GWMP.

NPS

To leave Turkey Run Loop Road: All visitors must exit via southbound GWMP. Motorists who need to access northbound GWMP, should continue to Route 123 to access northbound GWMP.
 
Map of GWMP Schedule A-C NB Detour
Northbound GWMP traffic traveling toward Maryland will need to exit at Route 123 and follow signs to reach I-495 north.

NPS

April Northbound Parkway Weekend Closures for Roadwork

This month, the NPS will temporarily close the northbound lanes of the GWMP between the Route 123 interchange and I-495 on select weekends, weather permitting. These closures are necessary for drainage installation, roadway demolition, and paving activities. Northbound Parkway Closure Schedule: Route 123 Interchange to I-495
  • First Weekend: From 7 a.m. on Saturday, April 19 until 6 p.m. on Sunday April 20
  • Second Weekend: From 7 a.m. on Saturday, April 26 until 6 p.m. on Sunday April 27
Motorists traveling northbound toward Maryland must exit at Route 123 and follow detour signs to reach I-495 north towards Maryland as shown on the detour map. During this time, visitors should follow the detour to northbound I-495 and proceed to southbound GWMP to access Turkey Run Park.
 
Map of southbound closure and detour
Southbound GWMP traffic will need to exit at Route 123 and follow signs to Spout Run Parkway to re-enter GWMP.

NPS

Route 123 to Spout Run Parkway Construction Outlook

Crews have completed the traffic shift to the newly constructed northbound lanes. As part of the next phase of the North Parkway Rehabilitation Project, one southbound lane will remain closed for construction through 2025. There will be no reversible lane in this section of the parkway. All work is weather permitting and subject to change.

New Lane Configuration (Route 123 – Spout Run Parkway): Early 2025 – Late 2025
  • PM Rush Hour (2:45 – 7:15 p.m.): One lane will carry traffic southbound toward Washington D.C. and two lanes will carry traffic northbound toward Maryland/Virginia.
  • All other times: There will be one lane open to traffic in each direction.
April Southbound Parkway Weekend Closures for Roadwork
This month, the NPS will temporarily close the southbound lane of the GWMP between the Route 123 interchange and Spout Run Parkway on select weekends, weather permitting. These closures are necessary to allow crews to perform drainage installation and roadway demolition activities. Southbound Parkway Closure Schedule: Route 123 interchange to Spout Run Parkway
  • First Weekend: From 7 a.m. on Saturday, April 19 until 6 p.m. on Sunday April 20
  • Second Weekend: From 7 a.m. on Saturday, April 26 until 6 p.m. on Sunday April 27
 
A graphic depicting work occurring in the left most lane while three other lanes have traffic.
During the evening rush hour, two lanes will carry traffic northbound toward Maryland / Virginia. There will be one lane of traffic in each direction at all other times.

NPS

Route 123 to Windy Run Bridge

Crews began construction activities on the right southbound lane including:

  • Drainage installation
  • Curb installation
  • Roadway and guardrail demolition

Crews continue lane striping in the parking area at North Donaldson Overlook. Fort Marcy and the North Donaldson Overlook remain inaccessible between 9 a.m. - 5:30 a.m.

 
A graphic depicting the set up of the traffic lanes.
During the evening rush hour, two lanes will carry traffic northbound toward Maryland / Virginia. There will be one lane of traffic in each direction at all other times.

NPS

Windy Run Bridge to Spout Run Parkway

The right southbound lane is closed for construction activities including:

  • Drainage installation
  • Curb installation
  • Cement treatment
 
A graphic depicts construction workers in the Southbound lane, while traffic moves in three lanes (two nouthbound and one sorthbound) next to it.
During bridge work, a three-lane configuration will be in place with a barrier to separate traffic from the work zone.

NPS

Bridge Construction

Crews continue with bridge work:

  • Turkey Run, Donaldson Run, Glebe Road, Windy Run, Dead Run, Pimmit Run, Gulf Branch, Route 123 interchange, and Spout Run Arch Bridges: Repairs on and below the bridge surface.
  • The containment platform remains in place at Turkey Run loop with limited clearance between the platform and the bridge.

Temporary barriers remain in place at Pimmit Run, Glebe Road, Gulf Branch, Donaldson Run, Dead Run, Windy Run, and Turkey Run bridges with narrower lane widths as work continues. No additional traffic delays are anticipated at this time.

 

Construction Zone Safety

Please slow down and be cautious while driving through work zones on the parkway.

  • Drivers should observe traffic signs for updated information.
  • A 40 MPH speed limit remains in effect from the I-495 interchange to Spout Run Parkway to help keep construction crew and motorists safe. This speed limit will be in place for the remainder of the project and is enforced as such.
  • To avoid traffic delays on the northern section of the parkway, drivers should consider alternate routes and plan for additional travel time.
  • Remember vehicles over 10,000 lbs. are always prohibited from using the parkway.
 

Construction Signage on the North Parkway

 
Map of the North Parkway with Construction Signage
This is the temporary construction signage motorists will see while traveling along the North Parkway.

NPS

 
 

Frequently Asked Questions (FAQs)

 
Aerial view of Route 123 and the proposed GWMP Interchange Option One. The curved sections in purple would be removed and the proposed configuration is in blue and is more linear. The Limits of Disturbance boundary is a dashed yellow line.
 

North Parkway News

Loading results...

    Park footer

    Contact Info

    Mailing Address:

    George Washington Memorial Parkway Headquarters
    700 George Washington Memorial Parkway

    McLean, VA 22101

    Phone:

    703 289-2500

    Contact Us