Yellowstone
Historic Resource Study
The History of the Construction of the Road System in Yellowstone National Park, 1872-1966
|
|
Part One: The History of the
Construction of the Road System in Yellowstone National Park, 1827-1966
and the History of the Grand Loop and the Entrance Roads
|
CHAPTER XII:
HISTORY OF GRAND LOOP ROAD
WEST THUMB TO LAKE JUNCTION
One of the prominent but hidden features of this road
section is the geologic feature, the Natural Bridge. Philetus Norris'
survey for possible routes in this area, he found the bridge to be his
answer for bypassing the sandy spits, ponds, and numerous gullies near
Bridge Bay. The bridge showed evidence of its use as a long-time game
trail and Norris felt that as soon as funds became available, he would
prepare the bridge for tourist use. In his 1880 report to the secretary
of the interior, Norris described the area:
What is now the bridge was once the brink of a
cataract nearly one hundred feet high, over a ledge of peculiarly hard,
durable, variegated trachyte upheaval to the vertical across the stream.
Directly across this ledge countless ages of erosion have formed first a
shallow, trough-like channel; then, or simultaneously with this channel,
a vertical orifice, several feet long by one foot wide, between the
strata, some two feet from the brink. There is farther upstream . . .
one of the finest archways I have ever seen, has about ten feet of stone
support for a carriage way above, and about thirty feet of waterway
beneath. The chasm is fully spanned by the bridge, which, by
measurement, I found to be twenty-nine feet long, and including the
above mentioned vertical orifice, ten feet high above the top of the
arch, and forty-one feet to the bedrock of the chasm, which, at this
point is a rapidly deepening cascade. As the two outside layers of the
vertical orifice, as well as the ancient channel, can readily be filled
or floored with timbers. . . . This route will be on of the most
traveled, and this natural bridge one day be crossed by thousands of
pilgrims to this wonderland. [104]
Historical records indicate that the road across the
Natural Bridge was not built by Norris and the travelers continued to
use the Mary Mountain route to Yellowstone Lake until 1891 when a road
followed the shore for much of the way from West Thumb to the lake
outlet. In 1895, Captain Anderson completed a road from the Lake Hotel
to the Natural Bridge. [105] In 1899, Hiram
Chittenden began to plan the construction of 8 miles of road across the
peninsula to replace the 12 miles of road built in 1891. The 1891 road
that followed the shore had been severely eroded by the lake and had
been abandoned and the portion that passed through the wooded section
had been constructed over uneven and rough ground. Chittenden believed
that this road was "the most monotonous drive in the park" [106] and that the road he planned would reduce
the distance by four miles, it would be a better road and that the road
would offer the visitors a view of the Natural Bridge. Chittenden
estimated that the new road would cost approximately $2,000 per mile or
a total of $16,000. In 1902, the new road was "put over the mountain by
way of the natural bridge and the knotted woods" and the old section
along the shore was abandoned. [107] In 1908,
the road was surfaced and ditched and the 1909 report listed the road as
in "very good condition." [108]
In 1923, the route from Lake Junction to West Thumb
was evaluated again. The National Park Service's engineering division
found the:
existing road between Arnica Creek and Bridge Bay
passes over high divide, necessitating a hard climb on one side and an
equally difficult descent on the other. This 9 miles section is entirely
void of scenic attractions and is a difficult piece of road to maintain
because of steep grades and the absence of water for sprinkling. It is
proposed to reconstruct the old original road along the shore of the
lake, making an attractive drive on practically a water grade, and
abandon the present road over the hill. . . . This crew (Cosey's Crew)
is now moving to West Thumb to rebuild the log bulkhead along the lake
shore. They should also place culverts and make fills in places of the
three log bridges between West Thumb and Arnica Creek. [109]
Two years later, this section of road was included as
part of the first 3-year improvement program with the intentions for
this portion to be completed in 1925. In a letter to the director,
Albright described the project:
I have discussed this project very thoroughly with
our engineers and we have reached the conclusion that we can do this
work cheaper by force account. If this was a case of constructing an
entirely new road, there would be no question but what is ought to be
done by contract. However, it is purely a matter of reconstruction. The
old original road between Thumb and Lake Hotel followed the Lake shore
quite closely as you note from old maps. In 1901 this road was abandoned
when the cut-off road was built across the mountains. This cut-off road
was apparently built to shorten the distance, but in order to make the
change it was necessary to construct a highway with grades running up to
16 percent. The road possesses no scenic qualities whatever, has many
sharp turns and narrow places where cars cannot pass and as I have just
stated a maximum grade 16 percent. When the old road was abandoned in
1901, it was usable for several years, apparently was used; however,
gradually the culverts and bridges which were of wood decayed and for
the past 20 years the road has been impassable except to saddle horses
and pedestrians. I have been over the road several times and there are
many miles that are in excellent condition today; all these stretches of
road will require widening and installation of drainage structures
which, under our plans, will be galvanized iron culverts of proper
sizes. We expect to do away with the two or three bridges by putting in
culverts and making fills. In three places the road will be realigned in
order to give better scenic effects of Lake Yellowstone, but these
stretches are short. [110]
By 1926, the reconstruction of the 11 miles stretch
along Yellowstone Lake between Bridge Bay and West Thumb replaced the
steep, narrow, and uninteresting section that went over the hill. A 3/4
mile section at Bluff Point had been widened. [111] Major landscape improvements were made to
this section as part of the parkwide road cleanup project funded by John
D. Rockefeller, Jr. [112]
The road which had been brought to the standard of
the other main park roads, with the exception of side drainages, was
oiled in 1928, and a new 2 inch oil top placed upon it during 1931. The
1931 oiling expedited the necessity for improvements to the side
drainages to lower the water table under the road to avert corrugation
from capillary action. [113]
In 1935 a field survey was completed for this road
section, however no more major work was done until the Mission 66 period
other than replacing 1,500 linear feet of guardrail with guideposts. [114] The Final Construction Report for work on
this section during 1960-61 listed the project as:
The major improvement on this project begins at the
Natural Bridge Road, approximately four miles south of Lake Junction, at
Station 888, elevation 7753, and extends northerly 3414.82 feet to
Station 922, elevation 7759. At Station 894+50, the road crosses the
inlet to the Bridge Bay Lagoon on a 237 feet 8 inches three-span steel
welded plate girder structure. All of the main improvement are on new
alignment except for the last 200' to 300' on the north and where a tie
is made to the existing Grand Loop Road. Immediately to the south, the
project abuts the Bridge Bay-Arnica Creek project, which is now under
construction. To the north of the project is a section extending to Lake
Junction, approximately 3 miles long, which is still unimproved to
Mission 66 standards. [115]
Other work completed on the project was the
construction of spur roads, one extending 2,000 feet to the west end of
the Bridge Bay Lagoon and another extending 400 feet to a future lake
front parking area for fishermen's use. By the end of 1963, Long
Construction Company of Billings, Montana, had completed the work
totaling $861,986.23. This section of road had received clearing,
grading, an emulsified stabilized base course, a wearing surface of
plant mix base course, bituminous and concrete curbs for traffic and
water control, and a box culvert on Bridge Creek. The old Gull Point
by-pass section was converted to a fishermen access and the construction
of the Lake by-pass was begun in late 1969. [116]
yell/hrs1/hrs1-12e.htm
Last Updated: 01-Dec-2005
|