Update: Site Observation Update Week of April 14

April 20, 2020 Posted by: Ranger Jeff

Update: Site Observation Update Week April 14th

With great weather, great momentum, and a steady stream of materials and supplies arriving daily, the project continues to come together in impressive ways. While the work this week can’t be described, yet, as “finishing touches”, it reflects the attention to detail that we expect will carry through to a refined finished product. The building’s lines have begun to reveal themselves, and hints at what the interior exhibit space will look like are revealing themselves. All together, this week’s work has been impressive.

It’s important to note that all crew members are employing all those health and safety measure that we are all practicing, including social distancing. Work crew members are being monitored regularly, and sanitation facilities are available for the crew. While the project is certainly important, the health and safety of employees and workers is much more important.

Front elevation with completed sheathing
Photo (A), taken from the southwest corner looking northeast shows the finished sheathing work, and posts that will support the trellis that will accent the front of the structure waiting installation.

Interior looking toward vesibule
Image (B) is taken from inside looking toward the front entrance showing supports that will hold an exhibit wall. Note the steel doors to the right awaiting installation.

Interior view of utilities closets and admin area
Photo (C), is taken from the administrative entrance looking toward the interior of the building. To the right you can see the framing for closets that will hold computer equipment, an office, a small storage area, and a work area for rangers.

Image (D) below shows a mock-up of a window installation which will be approved before any windows are installed.


Exterior view of a window mock-up before installation
In image (E) below we see a crane hoisting roofing insulation panels up for installation. The panels are comprised of rigid insulation sandwiched between sheets of plywood.

This week, an inspector was on site a good part of the day reviewing all aspects of the framing package, particularly roof diaphragm construction, shear walls, and hold downs. All aspects were found to be in full compliance and well-constructed.

Crane raising roofing insulation
The orange WRB (Water Resistant Barrier) you see going on in photo (F) is intended to protect the walls and interior structure from moisture intrusion. This is particularly important in our wet PNW climate. Rather than being stapled on, as is the case with other building wraps, WRB has a self-adhering backing which bonds directly to sheathing creating a tighter seal, and improved protection from the elements. And, its manufactured right her in the Pacific Northwest.

Orange WRB building wrap being installed
In photo (G), we see the entry vestibule being framed for the doors and glass which will accent the entry, and protect the interior space from weather rushing in. The word vestibule derives from Latin, probably meaning “a place to dress”. We don’t expect our vestibule will be used in that way.

Worker framing vestibule from inside of building
WRB installation continued on the southwest side of the building as you can see in photo (H). Once completely wrapped and tape sealed, the structure will be ready to receive its siding.

A view south to north of front elevation being wrapped with WRB
I tossed in image (I) below simply because I like that it shows the way our old friend, the sweeping Douglas Fir, shades the entry to the building, just as it did with the old structure. A beautiful tree.

View of covered entrance area with tree in foreground
Photo (J) shows the roofing membrane being installed. Just as WRB keeps out moisture on the sides of the building, this membrane keeps out moisture on the roof.

Roofing membrane installation

Worker building freestanding exhibit wall
Photo (K) above shows a worker erecting a freestanding exhibit wall in the center of the exhibit space that will hold, what else, exhibits.

In image (L) below we can see the support posts in place for the trellis that will accent the front of the building. The trellis will not only provide natural shading for the front, it will also support exhibit panels.

High posts are erected on south side to accept sheathing
In image (M) below, looking into the main exhibit space from the front of the building, we see blocking completed within the framing to support exhibit pieces and lighting that will come once the dry wall is installed.

Interior south wall showing framing blocking to accept exhibits
Photo (N), one freestanding, steel supported exhibit wall, fully sheathed and ready to receive its covering.

Completed freestanding exhibit wall
Photo (O), roof curbs for solar tube skylights.
Roofing curbs ready for tube skylights

Formwork at interpretive plaza ready for concrete
To complete the week’s updates, image (P) shows the concrete forms in place and ready to receive concrete for the interpretive plaza. There will be many things going on in this area, including a focus on the Native American cultures that existed here well before the arrival of Europeans.




 

AmericanCampVisitor Center, SAJH, construction



Last updated: April 22, 2020

Park footer

Contact Info

Mailing Address:

P.O. Box 429
Friday Harbor, WA 98250

Phone:

360 378-2240

Contact Us