Bandelier
Historic Structure Report: CCC Buildings
|
|
EXISTING CONDITIONS (continued)
BUILDING COMPONENTS (continued)
Vigas, Canales, Columns, and Lintels
At the outset of Package 224, the most critical
deterioration concern on the buildings was deteriorating wood
primarily vigas, canales, and columns. It was this "Rehab Decaying
Structural Members" that was identified in the project's initial 10-238.
Earlier applied oil preservatives had been lost over the years, and
exposure to rain and snow had promoted an environment of decay and
fungal attack. Natural checking within log members had only aggravated
this condition. Most of the viga deterioration was limited to the
exposed areas, but a number of vigas had deteriorated through the wall
and therefore deprived the member of its structure-bearing integrity
(figures 161-163). Many of the original viga ends had been periodically
replaced over the years. The prevalent method had been to remove the
exposed deteriorated end or stub and mortar a new stub in place. Many of
these stubs had since become loose and fallen (figure 164). Another
technique was to use opposing lag screws welded to a base plate as a
method to attach the new stub to the original viga (figure 165). On B-1,
B-6, B-7, and B-26, some or all of the exposed ends had been removed and
the resultant void filled in with a mud mortar similar to the original
plaster (figure 166). Similar deterioration was occurring on the
majority of canales. Many of the portal columns were decayed at their
bases, primarily because they were embedded in adjacent masonry surfaces
that trapped both moisture and soil (figure 167). From the crushing of
this rotten wood, several of the overhead parapets were deformed,
particularly the B-29 portal. Many of the edge latias and window and
door lintels had similarly deteriorated (figure 168). Much of the lintel
decay was caused by moisture running down the masonry wall and wicking
into the wood.
|
Figure 161. Viga deterioration through the wall of B-13 poses the
potential for structural failure, 1984. (Photo: Copeland for NPS)
|
|
Figure 162. Severe deterioration of wood viga ends, B-7, 1984. (Photo:
Copeland for NPS)
|
|
Figure 163. Severe deterioration on viga end, B-2. (Photo: Copeland for
NPS)
|
|
Figure 164. Area of viga stub replacement, B-29. Note fallen and
displaced stubs. (Photo: Copeland for NPS)
|
|
Figure 165. One method of attaching former replacement stubs using steel
plate and lag screws. (Photo: Copeland for NPS)
|
|
Figure 166. Two techniques of addressing deteriorated viga ends, B-6:
(1) cutting off exposed end and (2) cutting back exposed end and filling
in with mud mortar. (Photo: Copeland for NPS)
|
|
|
Figure 167. Column base deterioration, B-17, portal. (Photo: Copeland
for NPS)
|
Figure 168. Deteriorated lintel, B-25. (Photo: Copeland for NPS)
|
Following the approval of various work proposals
developed as components of this historic structures report, repair work
was initiated in 1986. [1] All existing canales
were replaced with an EPDM membrane that extended the copper canale
flashing onto the roof and parapet (figure 169). This work was done on
115 canales, 87 by contract and the balance through regional day labor
forces. The EPDM membrane was applied both as additional flashing and as
a potential base for future roof replacement.
|
Figure 169. Installation of secondary EPDM flashing over canale copper
flashing under way on B-13/14 portal. (Photo: Hose for NPS)
|
Canale scuppers at intermediate roof parapets were
replaced with 6-inch PVC scuppers on B-18 and B-32; on B-19, two
scuppers were completely removed and flashed with spray urethane.
Masonry over some of the canale openings had been previously removed on
B-13, B-17, and the B-15/16 portal, presumably to lessen ice buildup.
During this canale work, the masonry was restored on B-13 only; to do so
on the remaining areas would have involved impact on the existing
roofing and extensive flashing repairs.
Except for B-25, all vigas, columns, edge latias and
lintels were inspected, and where they had deteriorated they were
replaced in kind or repaired. This work was also done by regional day
labor forces; Viga repairs consisted of
full replacement in kind where deterioration had
significantly penetrated the building interior (B-13, B-21, and B-8's
woodshed)
structural epoxy repairs where deterioration had
penetrated the building interior but the log perimeter shell was sound
(B-21)
replacement of all deteriorated ends
patching with flexible epoxy at areas of minor
surface deterioriation
replacement of missing or fallen vigas
B-26's vigas had previously been removed to lessen
potential impact from passing vehicles. Because of the significant role
this building plays as the initial visual component of the park, these
members were reinstalled but with a shorter extension than originally to
avoid hitting increasingly larger recreational vehicles. The predominant
system of attaching these new ends was the "viga splice" method using
fiberglass rods and epoxy, a system reviewed and approved under the
preservation plan prepared for this work [2]
(figures 170 and 171). Through several years of working with this
technique, an additional technique of casting threaded fiberglass rods
into the stubs was developed and used on B-28 and B-29. Records were
maintained on the technique used for all repairs, records that will be
included with the project as-built drawings and the historic structures
preservation guide for the buildings. Deteriorated columns were replaced
in-kind but with a modified base detail using a raised concrete pad with
an embedded drift pin connector.
|
Figure 170. Structural epoxy repair, B-21, 1985. (Photo: Hose for NPS)
|
|
Figure 171. Structural epoxy repair and viga splice repair, B-13, 1985.
(Photo: Hose for NPS)
|
On new wood, members were sized to match the
original. Exposed surfaces were drawknifed to simulate the original
finish, exposed viga ends were given the original axed finish, and,
except for B-28 and B-29, the wood was pressure treated with chromated
copper arsenic. Originally, exterior wood was apparently left unstained,
but by the 1940s, preservative treatment was initiated. Currently, the
majority of all exterior structural wood has a dark stain attained from
a variety of opaque stains and oils; portal ceilings and interior
woodwork are primarily unstained but have achieved an aged, natural
patina. For new replacement wood, with the exception of B-28 and B-29
(where limited staining exists), staining was deemed appropriate to
blend the new with the existing exterior woodwork. In addition, staining
alleviated the green color resulting from the chromatic copper arsenic
treatment. Before staining, the treated wood was scrubbed with a 50
percent bleach solution, rinsed, and allowed to dry as long as possible.
In areas of total viga replacement, interior exposed surfaces were left
natural to blend with adjacent vigas, and the exposed end was spliced
like other viga splice work.
Two additional areas warrant mention. Two viga ends
have been removed from B-2 to allow hanging of the visitor center sign;
a metal pipe "flying canale" has been added to one of the canales of
B-18 to extend drainage farther from the building wall. In both cases, a
more sensitive response to the issue at hand could and should have been
pursued.
band/hsr/hsr5c.htm
Last Updated: 08-May-2005
|