Bandelier
Historic Structure Report: CCC Buildings
|
|
EXISTING CONDITIONS (continued)
BUILDING COMPONENTS (continued)
Walls
The structural integrity of the masonry walls appears
to be sound overall. Isolated areas of apparent settlement exist, most
notably in B-2, B-19, and B-27D. The cracking at the end of B-2's portal
(figure 172) is more a result of water leakage from above and movement
of the lintel than of actual settlement. [3]
This leakage is further evidenced by the latia staining and the amount
and nature of water-induced surface efflorescence present (figure 173).
Isolated areas of similar but lesser efflorescence exist on other
buildings. Because of the geological phenomena that deposited much of
the area's volcanic tuff, significant amounts of gas were entrapped,
making the stone a highly absorbent material. Because of this porosity,
efflorescence may be expected to flush out over time. The crack on the
exterior face of the portal (figure 174) appears stable. The former
crack in B-27D (figure 175) was replastered in 1986 and there has been
no apparent movement since. Other areas of settlement existed within the
parapets as a result of deteriorated column bases. Through borescopic
reading in 1985, voids as deep as 24 inches were found to exist under
the floor in B-19. [3] These voids were the
apparent result of past leakage of subfloor water pipes, threatened the
integrity of the stone flooring and adjacent masonry walls. Floor and
wall cracking indicated settlement of as much as 2 inches in the
interior wall. Recent filling in of these voids has corrected this
condition.
|
|
Figure 172. Wall crack in B-2 portal parapet. (Photo: Copeland for NPS)
|
Figure 173. Surface efflorescence from falling damp on B-2 portal
parapet. Note similar condition of rising damp on adjacent wall. (Photo:
Copeland for NPS)
|
|
|
Figure 174. A wall crack on the B-2 portal parapet. (Photo: Copeland for
NPS)
|
Figure 175. A plaster crack in B-27D before replastering. (Photo:
Copeland for NPS)
|
Along much of the north wall of the cabin complex
that faces the cliff's runoff, the masonry becomes saturated during
heavy rainfall. Given the type of stone and the severity of this runoff,
the walls are in surprisingly good condition. This condition can be
controlled as outlined elsewhere.
Mortar used within the stonework reportedly consisted
of three different mixes: one for the foundations, one for the walls,
and another for the parapets and their capping. Visual remains bear out
the report and reveal that the buildings' pointing is the struck setting
mortar. The majority are cement-based mixes, which, according to the
original specifications, ranged from 1:3 to 1:5 (cement: sand) with 10
percent lime added. This mix is appropriate to the stone's approximate
compressive strength of 850 pounds per square inch. A clay-based mortar
was used to a lesser extent, primarily within the wall planes. Recent
sampling and analysis for mortars and stuccos further support this range
of constituent compositions. The results of this sampling from 14
buildings will be included in the historic structures preservation guide
and data collection for the buildings. One noted characteristic of the
mortar is its slight variation among buildings and even within a single
structure. Repointing efforts over the years have been relatively
compatible in color and texture but often have a smoother, more smeared
tooling than the original. Their overall range and variety have
perpetuated the buildings' subtle variations. Recent repointing efforts
have often been too uniform and, in general, are incompatible with the
original mortar in color, texture, and tooling and adversely affect the
overall visual character (figure 176).
|
Figure 176. Detail of B-10 showing recent repointing efforts. Note the
cap installed on the attic vent. (Photo: Copeland for NPS)
|
Today, a significant amount of mortar has lost its
bond with the adjacent stone plane, allowing moisture to intrude. This
condition is particularly noted on the parapets, under canales, and
adjacent to wood members. The cement-based parging (stucco) at window
jambs and above lintels is in generally poor condition (figures
177-179). Much of the parapet coping parging is loose; the majority of
these areas have been surface coated with the roof membrane but not at
the exterior face. The cap on these parapets originally sloped to the
building roof. Subsequent repairs have changed much of this area so that
it now directs runoff onto the wall plane, thus increasing the potential
for absorption. Maintaining the integrity of the mortar joints and
parging is vital to the preservation of the buildings, as is maintaining
the design integrity of the parapet caps. Particularly on the entrance
road wall (B-31), many stones are loose or missing (figures 180 and
181). Although that wall is not part of this study, it deserves the same
maintenance attention and sensitivity as the remainder of the
buildings.
|
|
Figure 177. Detail of typical parging separation at a window jamb.
(Photo: Copeland for NPS)
|
Figure 178. Detail of typical parging separation at a lintel. (Photo:
Copeland for NPS)
|
|
Figure 179. Detail of typical parging separation at a lintel. Note the
mortar separation at the masonry overhead. (Photo: Copeland for NPS)
|
|
Figure 180. Detail of the entrance road wall (B-31), showing loose,
separated stone. (Photo: Copeland for NPS)
|
|
Figure 181. Detail of the entrance road wall (B-31), showing missing
stones. (Photo: Copeland for NPS)
|
Much of the original mud stucco (or sympathetic
reproductions of it) remains (figure 182). The trend toward using a
stronger, cement-based, painted plaster under portals, which began in
the 1940s for maintenance concerns, continues. This new material gives
the walls a much harder, cleaner appearance than the original mud mix.
Many of these painted wall bases under portals have a much higher
painted plane than earlier schemes and today have a scalloped edge
design. Although an exterior rendering may provide protection and a
certain amount of sealing to the stonework, it should be remembered that
the original coarse stucco was applied to provide a visual softening and
artificial aging to the structures aesthetic. Restucco efforts should
retain this design intent rather than be a mere stucco wash that totally
changes the essential character of the stonework (figures 183 and
184).
|
Figure 182. Detail of the original mud stucco, B-6. (Photo: Copeland for
NPS)
|
|
Figure 183. The rear of B-9, showing the original character of the
partially stuccoed masonry. (Photo: Copeland for NPS)
|
|
Figure 184. The rear of B-2, showing the change in masonry character as
a result of recent restucco efforts. (Photo: Copeland for NPS)
|
At some point, B-26 was given a Hypalon coating over
its exterior walls. This material, contrary to its intended purpose,
trapped embedded moisture and increased surface spalling. Under the
Package 224 work, the Hypalon was peeled away and a stucco coating
installed.
band/hsr/hsr5d.htm
Last Updated: 08-May-2005
|